Slow
and not operator friendly and whilst not completely unsafe
our risk assessment of our projects highlighted potential
problems. In order to achieve the production of approx 300lm
in a 4hr working window we would require an unacceptable level
of labour intensity. Labour which would be moving quickly
in a restricted area carrying very hot material by hand. We
decided to risk assess the current method out of the project
and decided to try and devise a safer and quicker system.
First of all we purchased 250gallon pre heater tanks
which heat the material and then maintain temperature control
by thermostat. We mounted these on trailers which we could
easily move with site transport.

Then we attached a specially developed heat lance to
extrude the hot bitumen directly into the chase in a continual
stream. Extrusion nozzle only needs to be guided by applicator.
Although material at 160 deg is passing through the lance
it is armour protected so that it cannot burst and it is cool
to touch. Machine is towed along length of chase as it is
sealed by the lance operator.
The
traditional method of infilling the chases (13mm wide by 100mm
deep) was to use hot oxidised bitumen at 160 deg C poured
into the chase using a steel watering can. In order to achieve
the target production (300lm per 4 hr shift) we estimated
as many as 12 men with watering cans were required. We felt
that this would place a higher than acceptable risk on these
men as they would have to walk back and forward to the bitumen
boiler with very hot bitumen in a steel watering can many
times a night in close proximity to one another. An incident
or a trip, fall or a collision between operatives was considered
high risk and we set out to look at an alternative safer method
of bitumen application.
We
discussed the problem within our contracts managers and supervisors
and came up with some ideas. It was difficult to find a solution
due to the nature of the material. At 160 deg C oxidised bitumen
is very fast flowing but will cool down rapidly when away
from a heat source. We decided to go to the specialist hot
materials handling industry and find out if there was a special
type of pipe or hose that could be adapted to fit on to a
large bitumen boiler. The hope was that if we could find such
a hose we could fit a special type of nozzle to deliver the
bitumen directly from the boiler to the cable chases without
the need to manhandle many small quantities of bitumen.
After
many attempts and re-design works the system was perfected
and first used on the 23-05 runway refurbishment at Stansted.
On average 250lm was achieved in a 4.5 hr possession the maximum
achieved was 485lm with 3 men using one bitumen application
machine.
This
level of production proved vital in the overall success of
the project making sure asphalt could be laid on time and
on programme.
|